NOTICE TO SHIPPERS AND CUSTOMERS
NORTHWEST ENTITLEMENT PERIOD
OFO LIFTED
January 19,
2007
Paiute is lifting the
Operational Flow Order for overruns issued on January 9, 2007. The
penalty provisions of Section 5.2(b) of the General Terms and Conditions
Paiute’s tariff will not be in effect beginning with the gas day of Saturday,
January 20, 2007.
Although linepack is stable, Paiute urges you to continue to schedule
your supply so that sufficient gas is being delivered to Paiute to cover gas
being taken off the system.
Paiute issued the OFO on January 9,
2007 because Northwest
had declared a Stage III Overrun Entitlement period subjecting Paiute to
penalties for any overruns greater than 13%. Effective Saturday, January
20, 2007, Northwest lifted
the entitlement, however, as mentioned above, Paiute urges customers to attempt
to avoid over pulls for the foreseeable future.
Any changes in the above information
will be passed along to Paiute’s customers immediately. Any questions regarding this information may
be directed to Mark Anderson, Paiute Pipeline Scheduling, (702)876-7332.