NOTICE TO SHIPPERS AND CUSTOMERS

Thursday, November 30, 2006

 

NORTHWEST ENTITLEMENT PERIOD OFO LIFTED

Saturday, December 2, 2006

 

Paiute is lifting the Operational Flow Order for overruns issued on November 29, 2006.  The penalty provisions of Section 5.2(b) will not be in effect beginning with the gas day of Saturday, December 2, 2006.  Paiute urges you to continue to schedule your supply so that sufficient gas is being delivered to Paiute to cover gas being taken off the system.

 

Paiute issued the OFO on November 29, 2006 because Northwest had declared a Stage III Overrun Entitlement period subjecting Paiute to penalties for any overruns greater than 13%. Effective Saturday, December 2, 2006, Northwest is lifting the entitlement, however, as mentioned above, Paiute urges customers to attempt to avoid over pulls for the foreseeable future.

 

Any changes in the above information will be passed along to Paiute’s customers immediately.  Any questions regarding this information may be directed to Mark Anderson, Paiute Pipeline Scheduling, (702)876-7332.