                               RATE SCHEDULE FT-1
                          FIRM TRANSPORTATION SERVICE
                                   (Continued)

3.  RATES (Continued)

          The maximum and minimum rates shall be those as set forth from
          time to time on the currently effective Sheet No. 10 of this
          tariff, which rates are incorporated herein by reference.
 
    3.2   In addition to the charges set forth above, Shipper shall:

          (a) Provide quantities to Paiute pursuant to Section 7 hereof for
              Gas Used by Paiute; and,

          (b) Pay any penalties, fees or other charges which may be 
              assessed pursuant to Section 5 of the General Terms and
              Conditions of this tariff.

4.  MINIMUM BILL

    The minimum bill per month shall be the Reservation Charges.

5.  RESERVED CAPACITIES

    Shipper's Reserved Capacities shall be specified in the executed
    Service Agreement between Paiute and Shipper providing for service
    under this rate schedule. The individual Reserved Capacities are as
    follows:

    5.1   The Daily Reserved Capacity shall be the largest daily quantity
          of natural gas Paiute is obligated to receive in total from
          Shipper at the Receipt Point(s) specified in the Service Agree-
          ment for firm transportation under this rate schedule during the
          Winter Period.

    5.2   The Summer Daily Reserved Capacity shall be the largest daily
          quantity of natural gas Paiute is obligated to receive in total
          from Shipper at the Receipt Point(s) specified in the Service
          Agreement for firm transportation under this rate schedule during
          the Summer Period.

6.  FACILITY ADDITIONS

    As a matter of policy, Paiute will not construct any additional main-
    line facilities, unless either such facilities are economically
    feasible consistent with Section 157.14 of the Commission's Regulations
    and Section 7 of the Natural Gas Act, or Shipper agrees to provide
    reimbursement for the total cost of facilities to be constructed as
    explained below.