TF03      240010004P126First Revised Sheet No. 24
TF04                Original Sheet No. 24   
TF05Edward C. McMurtrie, Vice President/General Manager
TF06110503                      120903
                             RATE SCHEDULE FT-1
                        FIRM TRANSPORTATION SERVICE
                                 (Continued)


6.  FACILITY ADDITIONS (Continued)

          at the various Receipt Points and any other similar factors
          which impact the extent to which the available capacity from
          the new facilities will actually be used. Based on these criteria,
          the economic value of a project shall be determined based upon a
          discounted cash flow rate of return methodology, with a minimum
          acceptable rate of return at least equal to the lesser of (a) the
          allowed rate of return of Paiute in its last general rate pro-
          ceeding plus three (3) percentage points, or (b) thirteen percent
          (13%).

    6.3   Miscellaneous -- Paiute shall not construct facilities hereunder
          which will compromise the operational integrity of Paiute's pipe-
          line system. Paiute will own and operate all facilities
          constructed hereunder.

7.  GAS USED BY PAIUTE

    Shipper shall provide its proportionate share of the Gas Used by Paiute
    in its day-to-day operations for transportation hereunder, in accor-
    dance with Section 4.2(e) of the General Terms and Conditions of this
    tariff.

8.  MEASUREMENT BASE

    Refer to Section 2 of the General Terms and Conditions of this tariff.

9.  FILING FEES

    Shipper shall reimburse Paiute for any and all filing fees incurred by
    Paiute in seeking governmental authorization for the initiation, exten-
    sion or termination of service under this rate schedule. Paiute shall
    not use such filing fee costs or the revenues so collected in the
    establishment of its general rates.