TF03      670010005P126First Revised Sheet No. 67
TF04                Original Sheet No. 67   
TF05Edward C. McMurtrie, Vice President/General Manager
TF06110503                      120903
                       GENERAL TERMS AND CONDITIONS
                                (Continued)


4.  OPERATING PROCEDURES (Continued)

    4.4   Determination of Receipts and Deliveries: (Continued)

              (5)  Fifth - Volumes scheduled from the LNG Plant that are to
                   be transported under Rate Schedule IT-1;

              (6)  Sixth - Volumes scheduled from and confirmed by an
                   upstream pipeline to Paiute for transportation by 
                   Paiute under Rate Schedule IT-1.

          (b) Determination of Deliveries: This section applies to those
              situations where the gas delivered by Paiute into the facil-
              ities of any Receiving Party is applicable to more than one
              transportation agreement.

              (1)  First - The volumes scheduled for payback from Paiute to
                   the Shipper under Rate Schedule FT-1;

              (2)  Second - The volumes scheduled from the LNG Plant that
                   are transported under Rate Schedule FT-1;

              (3)  Third - The volumes scheduled for transportation from
                   a Receipt Point under Rate Schedule FT-1;

              (4)  Fourth - The volumes scheduled for payback from Paiute to
                   the Shipper under Rate Schedule IT-1;

              (5)  Fifth - The volumes scheduled from the LNG Plant that
                   are transported under Rate Schedule IT-1;

              (6)  Sixth - The volumes scheduled for transportation from a
                   Receipt Point under Rate Schedule IT-1;